Air Infiltration in the corner of the window and just needs to be adjusted so it seals right.
Air infiltration where the outside deck ties into the house and just needs some low expanding foam.
Air infiltration where the outside deck ties into the house and just needs some low expanding foam.
Air infiltration and just needs some low expanding foam, this causing higher utility bills.
Miss performing or missing insulation in the wall causing air infiltration into the room causing higher utility bills.
Heat escaping from the inside of the house causing higher utility bills.
Air infiltration and just needs some low expanding foam, this is causing higher utility bills.
PREDICTIVE & PREVENTATIVE
Hot Fuse Clip
Hot Knife Connection
Overloaded B Phase
A Phase on a Three pull break going bad
Both of these issues in these pictures are in the same switchgear. The one above is showing a knife switch issue with the blade and the knife port. This is the B phase and is the main disconnect for the entire facility. The picture below is showing a bus bar issue and this is on the A phase. If either one where to give out it could cause the facility to shutdown or could potentially blow up causing a catastrophic fire and could kill some one. But with the facilities routine maintenance program we caught the issue in time and got it scheduled to a planed shut down with out any instances.
Insulation breakdown inside the boiler.
Bad seal on boiler door 231ºF
Old hard grease in bearing housing making the bearing hot 212ºF
Hot Whirly Bearing 236ºF
Hot Shaft Bearing.
Hot Motor 194ºF
CONSULTING
Infloor heat under tile floor
Infloor heat in concrete that needs to be jack lifted up with concrete so the two edges meet up. The contractor needed to know where the tubes were so they would not hit them when lifting up the concrete.